A90 south of Peterhead | Resurfacing
Scheme Summary
Scheme Updates
Rescheduled start and end dates
Issued: 15 March 2023
Due to adverse weather, this scheme will now be constructed as follows:
Thursday 16th and Friday 17th March.
Overnight convoy working: 7.30pm-6.30am.
Traffic management will be removed by 6.30am on Saturday 18th March.
Sunday 19th to Friday 24th March.
Overnight convoy working: 7.30pm-6.30am.
Traffic management will be removed by 6.30am on Saturday 25th March.
In order to complete the scheme, further works will be programmed in April and an update will be issued when available.
Rescheduled start date
Issued: 13 March 2023
Due to the ongoing forecast for adverse weather this week, the scheme is now scheduled to start on Wednesday 15th March at 7.30pm.
Rescheduled start date
Issued: 10 March 2023
Due to the forecast for adverse weather this scheme is now scheduled to start on Tuesday 14th March at 7.30pm.
OVERNIGHT SURFACING IMPROVEMENTS ON A90 SOUTH OF PETERHEAD BEGINS SUNDAY 12th MARCH
Amey is carrying out road surfacing improvements on a section of the A90 to the south of Peterhead from Sunday 12th March to Saturday 1st April.
The project will address defects on more than 2100 metres of the A90 carriageway from Mains of Longhaven to just south of Boddam.
The £820,000 scheme, which Amey is carrying out on behalf of Transport Scotland, will benefit more than 7000 vehicles who use this route each day, creating a smoother ride for motorists and reducing the need for ongoing maintenance.
Work has been scheduled to begin on Sunday 12th March to take into account the forecast for adverse weather in the preceding days.
To ensure the safety of roadworkers and motorists the work will be undertaken using an overnight convoy system between 7.30pm to 6.30am each night from Sunday 12th March to Friday 31st March.
There will also be the need for the use of occasional daytime temporary traffic lights to allow the cooling of treatments.
Access to and from Rocksley Drive at Boddam will be restricted at times during the works, with local diversions in place via Station Road.
Traffic management will be removed by 6.30am on Saturday 1st April.
Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.
- A free Road Work Alerts service is available from our website. An email address is all that is required to sign up for the service.
- To report a problem on the network please visit: https://netrunkroads.scot/report-a-problem/.
- Real-time journey information can be obtained by visiting www.trafficscotland.org or via Twitter: @TrafficScotland.
For media enquires please contact Amey’s press office on 01865 713240 or by email: press.office@amey.co.uk. Follow us on Twitter @NETrunkRoads.