Scheme Summary

Scheduled:
22-25 March 2023
Summary:
Carriageway Repairs

OVERNIGHT REPAIRS ON TWO M90 OFF-SLIPS IN FIFE AND PERTH AND KINROSS IN MARCH

Amey is carrying out essential overnight repairs on two separate southbound off-slips from the M90 in both Fife and Perth and Kinross during late March.

The surfacing repair work at the M90 junction 3 southbound (Fife) and junction 10 southbound (Perth and Kinross) off-slips will both require overnight road closures from 8pm-6am.

The essential maintenance, which Amey is carrying out on behalf of Transport Scotland, will take place at the following dates and times:

FIFE

  • Location: M90 southbound Junction 3 off-slip at Halbeath, Dunfermline
  • Dates/Times: Between Wednesday 22nd March at 8pm until Thursday 23rd March at 6am.
  • Closure: Total closure of the off-slip.
  • Diversion: A diversion will be in place directing southbound traffic to leave the M90 at Junction 1, then rejoin the M90 travelling northbound so they can exit at the M90 northbound Junction 3 off-slip.

PERTH AND KINROSS

  • Location: M90 southbound Junction 10 off-slip.
  • Dates/Times: Between Friday 24th March at 8pm until Saturday 25th March at 6am.
  • Closure: Total closure of the off-slip.
  • Diversion: A diversion will be in place directing southbound traffic to leave the M90 at Junction 9, then rejoin the M90 travelling northbound so they can exit at the M90 northbound Junction 10 off-slip.

FIFE JUNCTION 3

PERTH AND KINROSS JUNCTION 10

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.